Plastics Recycling Update

East Coast PRF on the road to reopening

Baltimore MRFWheels are in motion to resume operations at an idled plastics recycling facility outside Baltimore. But if it does start up again, it will do so without one of its original partners.

The Dundalk, Md. QRS facility, which launched as a joint venture between QRS Recycling and Canusa Hershman Recycling, suspended operations last summer. As a plastics recovery facility (PRF), the operation had been separating materials out of mixed-plastics bales for sale to downstream outlets.

At the time, the companies said the downtime would “enable an optimization of the equipment” at the facility, and they noted market challenges were impacting operations across the post-consumer resin industry.

Efforts have been progressing over the past six months to bring it back on-line, sources told Plastics Recycling Update. But in the meantime, QRS Recycling exited the joint venture as of November 2017, company QRS CEO Greg Janson confirmed, and the PRF is now owned entirely by Canusa Hershman Recycling.

“We are no longer involved in the QRS of Maryland facility,” Janson stated.

But as QRS exits, another player has expressed interest in acquiring the facility.

A new operator

The Closed Loop Fund originally provided financial backing to get the PRF operational. Bridget Croke, external affairs director for the Closed Loop Fund, told Plastics Recycling Update the facility has received a letter of intent from “a major company in the industry” and hopes to close on a transaction in the coming months. It would be an acquisition by a new operator, she said.

“Current market conditions have driven additional interest,” she added.

Few specifics are public at this point, as the parties are operating under a confidentiality agreement, said Jonathan Sloan, president of Canusa Hershman.

“We’ve been working diligently to find various parties who are interested in restarting the facility,” he said.

Sloan said China’s import restrictions and rising oil prices have contributed to renewed interest in the secondary sortation operation.

“We’re hopeful that, in the near future, we have consummated a transaction,” Sloan said, noting the relevant stakeholders would share more details when appropriate.

As for the facility’s moniker, given QRS’s departure, Sloan noted that will likely change as well.

“I would suspect any new owner would re-brand the facility to their name,” he said.

Pioneering in its field

QRS and Canusa Hershman opened the 128,000-square-foot Baltimore-area PRF in November 2015, focusing on separating materials out of Nos. 3-7 bales. The Maryland location was sited to serve regional materials recovery facilities (MRFs) and reclaimers, according to QRS. It had a capacity of nearly 55,000 tons per year.

Under the original partnership, Canusa Hershman’s role was to acquire feedstock for the facility, and QRS was responsible for operating it. Both companies had an equity position in the venture.

The QRS operation has been viewed as a pioneer in the push for domestic processing of mixed-plastic bales, which have traditionally been shipped overseas.

During the facility’s development, the project received a $2 million loan through the Closed Loop Fund. The project, which cost $15 million overall, was featured prominently in a New York Times profile of the Closed Loop Fund.

Shortly after the PRF idled last summer, the Closed Loop Fund discussed the situation in an interview with Plastics Recycling Update. Rob Kaplan, managing director of the fund, said the organization “knew there were a lot of challenges” for a facility like the Dundalk plant.

“Finding the right opportunity to capitalize the facility and put a business model together that will work in the long term is for the good of the model and is what we want to see,” Kaplan said at the time.

More stories about processing

To receive the latest news and analysis about plastics recycling technologies, sign up now for our free monthly Plastics Recycling Update: Technology Edition e-newsletter.

 

Exit mobile version