Resource Recycling
  • The Latest
  • Analysis
    • All
    • Certification Scorecard
    • Industry Announcements
    • Opinion
    Feds to develop repairable computer donation program

    The whitebox blind spot in PC recycling

    Analysis: circular design still elusive in laptops

    PC shipments grew in Q1, but questions remain

    The independent ITAD at a crossroads

    The independent ITAD at a crossroads

    Certification Scorecard — Week of April 20, 2026

    Apple Watch on product box.

    Wearables are coming and ITAD isn’t ready

    Certification Scorecard — Week of April 13, 2026

    EV Battery Pack - Sergii Chernov-Shutterstock

    Redwood, Rivian deal fuels US infrastructure plans

    Bloom ESG and e-Stewards roll out critical metals metric

    Colorado regulators suggest mid-range EPR scenario

    Why collaboration on plastic waste still matters

  • Conferences
  • Publications

    Other Topics

    Textiles
    Organics
    Packaging
    Glass
    Brand Owners

    Metals
    Technology
    Research
    Markets
    Grant Watch

    All Topics

Subscribe
No Result
View All Result
Resource Recycling
  • The Latest
  • Analysis
    • All
    • Certification Scorecard
    • Industry Announcements
    • Opinion
    Feds to develop repairable computer donation program

    The whitebox blind spot in PC recycling

    Analysis: circular design still elusive in laptops

    PC shipments grew in Q1, but questions remain

    The independent ITAD at a crossroads

    The independent ITAD at a crossroads

    Certification Scorecard — Week of April 20, 2026

    Apple Watch on product box.

    Wearables are coming and ITAD isn’t ready

    Certification Scorecard — Week of April 13, 2026

    EV Battery Pack - Sergii Chernov-Shutterstock

    Redwood, Rivian deal fuels US infrastructure plans

    Bloom ESG and e-Stewards roll out critical metals metric

    Colorado regulators suggest mid-range EPR scenario

    Why collaboration on plastic waste still matters

  • Conferences
  • Publications

    Other Topics

    Textiles
    Organics
    Packaging
    Glass
    Brand Owners

    Metals
    Technology
    Research
    Markets
    Grant Watch

    All Topics

Subscribe
No Result
View All Result
Resource Recycling
No Result
View All Result
Home E-Scrap

Industry experts talk data centers, component values

Colin StaubbyColin Staub
May 9, 2024
in E-Scrap
Industry experts talk data centers, component values

Artificial intelligence and cryptocurrency are contributing to positive market conditions in the ITAD industry, and a number of company leaders anticipate the upward trend will continue.

Although they’re both hot topics in the general economy, they have key impacts in the ITAD sector: AI is driving exponential growth in the data center market, and cryptocurrency mining is providing a boost to used device markets — particularly welcome news for ITAD operators after a couple years of depressed component pricing.

E-Scrap News spoke with a few ITAD firms and analyzed publicly traded company reports to learn about the trends shaping the ITAD market.

“There are a lot of really great tailwinds that we’re riding here,” said Keith Layton, vice president of hyperscale remarketing at TES. “I see nothing but positive, not only for us but really for the whole ITAD industry.”

Industry-wide push into a growing market

E-Scrap News first wrote about data center decommissioning in 2019, when Sims Recycling Solutions — now Sims Lifecycle Services — and ITRenew — since purchased by Iron Mountain — described plans to move into this emerging sector of the industry.

A lot has changed since then. Far from being a niche in the industry, data center decommissioning has become a central portion of some major ITAD firms’ business activities. Back in 2019, it was being driven by the continuing growth in cloud computing. That, of course, skyrocketed during the COVID-19 pandemic and continues to grow all the time. Artificial intelligence is the latest force driving growth in the data center industry.

There are some obvious reasons ITAD companies like handling the devices housed within data centers. 

“They’ve been run in a controlled environment, they’re not banged up like a laptop gets,” Layton explained. “They’re well-maintained, so they’re pulled as working units, not, ‘It’s broken, so I’m replacing it.'”

TES is among the major ITAD players that has pushed into the data center decommissioning space, most recently opening up a new facility in Virginia to focus specifically on that business segment.

“That’s definitely much more material now than it was a year or 18 months ago as part of our overall volume,” said Eric Ingebretsen, chief commercial officer at TES. That growth has come as the company has seen stability, but not significant increases, in its laptop and desktop business.

Other major players have continued their push into the space as well. Data center decommissioning is now a core part of Sims’ ITAD business — the company even relocated a precious metals division out of its asset recovery business and into Sims Metal last summer, noting that the move reflects the ITAD operation’s “strategic focus on repurposing data centers.”

Iron Mountain has also continued its data center work: In the company’s first-quarter earnings call on May 2, CEO Bill Meaney reported Iron Mountain recently won a contract to handle data center decommissioning for a “multinational conglomerate company.” Company leaders said the data center work is driving up total volume handled through the company’s ITAD segment, and they expect that will continue.

The TES leaders noted smaller ITAD firms are also testing the waters of data center work, although Layton pointed out larger players have the advantage of global reach. That’s attractive to customers operating in multiple markets, who often like to work with a single provider. Iron Mountain hinted at that advantage in describing its recent data center deal, noting it was “pleased to be able to provide a holistic global solution” to meet the customer’s needs.

The increase in companies entering this space isn’t necessarily translating into fierce competition just yet, because the data center industry itself is also growing.

“The pie continues to get bigger,” said Bill Vasquez, general manager of TES Americas. He noted the data center space exploded from 2017 through 2020 and grew even more during the pandemic. Now AI is driving further data center growth, not only increasing demand for data centers but also changing how data center operators design and outfit the facilities.

All of that points to ongoing and increased equipment turnover to meet the changing demands of the data center world.

There are some challenges in retiring assets from a growing and fast-evolving market like the data center space. The useful life of data center assets has gone from what used to be three to five years, up to five to eight years and even longer, Layton said. Having a longer gap between equipment refreshes creates a bit of a crunch for ITAD companies that handle that material. But the growth in the overall number of data centers could offset that lag time.

Component prices continue to rebound

The last few years were a rollercoaster ride for resale values. Early in the pandemic, ITAD firms saw unprecedented demand for their refurbished devices, leading to a runup in prices even as they saw their inbound device stream dry up.

But that boost in pricing paved the way for a hard fall.

“Everything that goes up must come down,” said Anuar Garcia, CEO of GreenTek Solutions, a Texas-based ITAD firm, in a recent interview.

The pricing collapse for used devices and components played out throughout 2022 and 2023. Data from ITAD firm Cascade Asset Management tallied a 40% drop in used laptop pricing in 2022. Garcia noted it was equally or even more challenging for ITAD operators than the height of the pandemic because of the fast price decrease. Demand for ITAD services also lagged below its pre-COVID-19 levels, Garcia added, but that has begun to change in 2024.

“This year has been very interesting, because we feel the demand for ITAD services has come back to where it was before COVID,” Garcia said.

Component pricing has also been on a steady recovery, beginning at the end of last year and moving into 2024, Cascade reported in February. TES leaders similarly described strong growth. Vasquez noted laptops and desktops saw a consistent rise throughout 2023, while CPU and memory drives spiked significantly at the end of the year.

Layton says cryptocurrency plays a big part in those component prices improving. The SEC in January approved rule changes that allow cryptocurrency exchange-traded funds, or ETFs, to be listed on U.S. stock exchanges, a move the federal authority had rejected for years. That move corresponded with a surge in cryptocurrency prices, which means more people mining crypto, which is typically driven by either a computer’s memory or graphics card. So when crypto rises in value, those components become highly sought after, and the demand leads to rising prices.

“That directly correlates to the secondary market,” Layton said.

Crypto mining also correlates with demand for peripheral components like device power supplies, Layton added. TES also saw a recent spike in demand for SSD hard drives.

Iron Mountain reported similar component pricing improvement in its earnings report last week. The company described “strong organic growth” in its ITAD business “driven by a combination of increased volume and component price recovery leading to a strong quarter.”

In the company’s earnings call, Iron Mountain Chief Financial Officer Barry Hytinen said the company’s ITAD division revenue came in about $10 million higher than the company had projected in its first-quarter guidance, largely because of those improving prices. The company saw prices especially increase late in the first-quarter, he said, and they have continued to rise into the second quarter. Hytinen said the company expects prices will continue that trend throughout the year.

Tags: Markets
TweetShare
Colin Staub

Colin Staub

Colin Staub was a reporter and associate editor at Resource Recycling until August 2025.

Related Posts

Volatility reshapes outlook for US metals businesses

byScott Snowden
April 15, 2026

Panelists at the ReMA conference in Las Vegas said tariffs, reshoring and geopolitical tension are remaking trade flows, lifting US...

NERC launches hub to promote PCR demand 

byAntoinette Smith
April 15, 2026

The Northeast Recycling Council's PCR Material Demand Hub offers resources for government procurement, material- and product-specific resources, and certification and...

Industry group: Help us find the plastic bale volumes we need

PET bales sink further as other grades firm 

byRecyclingMarkets.net Staff
April 15, 2026

Pricing for HDPE and PP bales rose again, while PET bales remained low, film grades have steadied, and paper and...

Lead battery recycling market set for steady growth

byScott Snowden
April 14, 2026

The global lead battery recycling market is projected to grow steadily through 2034, supported by regulation, automotive replacement cycles and...

GFL acquires SECURE Waste for $6.4bn

byStefanie Valentic
April 13, 2026

GFL Environmental has agreed to acquire SECURE Waste Infrastructure Corp. in a $6.4 billion deal that expands the waste hauler's...

Trafigura signs $1.1b deal for recycled battery metals

byScott Snowden
April 8, 2026

Trafigura entered the agreement to expand access to recycled critical materials, supporting efforts to build more resilient battery supply chains...

Load More
Next Post
Dozens of free collection sites coming to Pennsylvania

Dozens of free collection sites coming to Pennsylvania

More Posts

Birch Plastics gets FDA green-light for post-industrial PP

LyondellBasell upgrade to PreZero assets on hold

April 23, 2026
The independent ITAD at a crossroads

The independent ITAD at a crossroads

April 22, 2026
Towfiqu ahamed barbhuiya

Before the Bin: Breaking down food date labeling

April 20, 2026
Industry group: Help us find the plastic bale volumes we need

PET bales sink further as other grades firm 

April 15, 2026
EPR fees are a market signal. Here’s what they’re telling you.

Oregon DEQ flags 250 producers for RMA noncompliance

April 21, 2026

Google pilots reuse kits to extend device life

April 21, 2026
EPR fees are a market signal. Here’s what they’re telling you.

EPR fees are a market signal. Here’s what they’re telling you.

April 10, 2026
Battery recycler Ascend Elements files for bankruptcy

Battery recycler Ascend Elements files for bankruptcy

April 13, 2026
Data erasure firm expands wearable device capabilities

Apple hits 30% recycled content, debuts new recovery tech

April 17, 2026

NERC launches hub to promote PCR demand 

April 15, 2026
Load More

About & Publications

About Us

Staff

Archive

Magazine

Work With Us

Advertise
Jobs
Contact
Terms and Privacy

Newsletter

Get the latest recycling news and analysis delivered to your inbox every week. Stay ahead on industry trends, policy updates, and insights from programs, processors, and innovators.

Subscribe

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

No Result
View All Result
  • The Latest
  • Analysis
  • Recycling
  • E-Scrap
  • Plastics
  • Policy Now
  • Conferences
    • E-Scrap Conference
    • Plastics Recycling Conference
    • Resource Recycling Conference
    • Textiles Recovery Summit
  • Magazine
  • About Us
  • Advertise
  • Archive
  • Jobs
  • Staff
Subscribe
This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.